From April 2025 to June 2026 GIMAN crews completed 35 installations and re-installations of the mechanical 4-way joint solution on Siemens W501F units, FD3 and FD4, in Texas, Arizona, Oregon, California, Alabama and Ontario, Canada. We execute it in the field for Nord-Lock Group, maker of Superbolt and Boltight.
The problem: a joint that leaks across the fleet
The 4-way joint is where the horizontal joint meets the vertical joint between cylinders. Thermal cycling distorts the cylinders, the faces lose contact and combustion air escapes. For years the answer was a welded leak box, which only contains the leak.
How we install it, inside the outage
- Preparation. Inventory, cleaning of holes and faces, tensioner pre-assembly and seal cutting.
- Hydraulic closure. One Boltight pump pressurises every position on each side of the cylinder.
- Alignment and load transfer. Misalignment is corrected under load and Superbolt tensioners are tightened without releasing pressure.
- Seal and hand-over. Segmented internal seal with retainers, final gap readings and photo report.



What the plant gets at the end: torque values for every tensioner, as-found and as-left alignment readings, a photo record of every retainer and seal position, and the field service report. Full 501F page · procedure and photos
Your FD3 or FD4 shows the signs?
Combustion air at the joint, faces that no longer seal: let’s look at it before the next outage.