On an offshore asset every hour of downtime hits production, cost and safety at the same time. Before this job, maintenance on critical equipment such as gas compressors and transfer pumps took 48 hours or more per intervention: specialised crews, high-pressure hydraulic gear, and frequent re-tightening because the joint did not seal on the first pass.

Where it started: the trial on one flange
In June 2018 we surveyed the assembly and start-up of a high-pressure compression module at the POL-A process centre. Flanges from 2 to 36 inches were bolted at night, in tight spaces, with hammer wrenches and hydraulic torque. We ran the trial on the same flange, Superbolt against hydraulic torque:
Abkatún-A: our crew on board
In December 2019 we installed Superbolt on the compression-module joints of Abkatún-A, from the 36-inch class 600 flanging module to the 2–8 inch PSV, fuel gas and drain lines, with a torque audit of every tensioner. On the retention cones and blinds of one module the job went from 72 hours to 25, and the module started up 47 hours earlier at every maintenance.
The result, in the client’s words
Sealing on the first tightening, one person with a conventional torque wrench, no external hydraulic equipment, and knowledge transferred to the operating staff. Intervention times dropped to 8 hours.
“With GIMAN’s solutions we cut our maintenance times from 48 hours to just 8, eliminating rework and improving safety and operating efficiency.” · Abkatún Alfa team, PEMEX
How the tensioner works, the BOP and wind applications and the full numbers: Superbolt page · info.giman.com/bolting